๐Project Closed๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Running Track Replacement
1023 Abe Lincoln Ave, Port Arthur, TX 77640, Port Arthur, TX, 77640
Completed100%
๐Project Metrics
TDLR #TABS2021013747$850K
Project Value
41,800
Square Feet
$20/sqft
Cost/SqFt
5 months
Duration
Registered:Apr 20, 2021
Start:Mar 26, 2021
Target:Aug 16, 2021
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Remove existing track and replace with new 8-lane track.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
April 20, 2021
Construction Start
March 26, 2021
Expected Completion
August 16, 2021
๐Related Projects
๐คSame Owner
$3.5M total๐๏ธSame Design Firm
$1.1M totalProperty Owner
Design Firm
๐๏ธ
Texas Sports & Civil Engineering, LLC.
2 projects ยท $1.1M