๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

Thirty Five Plaza Suite 210

5810 San Bernardo Suite 210, Laredo, TX 78041, Laredo, TX, 78041
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2021014660
$65K
Project Value
1,310
Square Feet
$50/sqft
Cost/SqFt
5 months
Duration
Registered:May 3, 2021
Start:May 30, 2021
Target:Oct 31, 2021
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Office Finish Out

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 3, 2021
Construction Start
May 30, 2021
Expected Completion
October 31, 2021