๐Review Complete๐ง Additions to Existing Building๐ต This project involves public funds, public land, or is a Federally funded roadway project.
American Airlines-Terminal C-High C Gate Interior Fit-out
2330 N International Parkway, Dfw Airport, TX 75261, Dfw Airport, TX, 75261
Construction50%
๐Project Metrics
TDLR #TABS2021016611$18.0M
Project Value
110,000
Square Feet
$164/sqft
Cost/SqFt
1y 1mo
Duration
Registered:May 27, 2021
Start:Jun 1, 2021
Target:Jun 30, 2022
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Interior finish-out of ramp level support spaces and concourse level gate spaces for gates 35 through 39
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
May 27, 2021
Construction Start
June 1, 2021
Expected Completion
June 30, 2022
๐Related Projects
๐คSame Owner
$33.1M totalProperty Owner
๐ค
DFW Airport
Contact: Iliana Diaz
4 projects ยท $33.1M
2400 Aviation Dr, DFW Airport, Texas 75261
Design Firm
Tenant
๐ข
John Haywood