๐Project Closed๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Smith Middle School Weight Room Addition
900 S San Patricio St, Sinton, TX 78387, Sinton, TX, 78387
Completed100%
๐Project Metrics
TDLR #TABS2021018956$924K
Project Value
2,000
Square Feet
$462/sqft
Cost/SqFt
8 months
Duration
Registered:Jul 1, 2021
Start:Nov 8, 2021
Target:Jul 11, 2022
๐
Project Closed
Project has been completed and closed
๐Scope of Work
The scope of work is a 2000sf PEMB that will serve as a weight room. The PEMB will be conditioned space with a vestibule, custodial, and MEP room.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
July 1, 2021
Construction Start
November 8, 2021
Expected Completion
July 11, 2022
๐Related Projects
๐คSame Owner
$84.7M totalProperty Owner
๐ค
Sinton Independent School District
Contact: Ms. Melissa Villarreal
3 projects ยท $84.7M
322 S. Archer Ave, Sinton , Texas 78387