GoPuff FW Midro Fulfillment Center

8751 Camp Bowie Blvd. #400, Fort Worth, TX 76116, Fort Worth, TX, 76116
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2021019219
$175K
Project Value
4,932
Square Feet
$35/sqft
Cost/SqFt
4 months
Duration
Registered:Jul 6, 2021
Start:Aug 9, 2021
Target:Dec 7, 2021
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Demolition of existing walls and ceiling. New construction is the finish out of the shell building into a Grocery Store Micro Fulfillment Center.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 6, 2021
Construction Start
August 9, 2021
Expected Completion
December 7, 2021