North Munger Boulevard - Group 17-1410

Block 500N to 800N, Dallas, TX 75214, Dallas, TX, 75214
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022001189
$1.7M
Project Value
89,590
Square Feet
$19/sqft
Cost/SqFt
2y 7mo
Duration
Registered:Sep 17, 2021
Start:Feb 14, 2022
Target:Aug 31, 2024
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Reconstruct existing 4-lane median divided curb & gutter street; reconstruct North Munger Blvd. from Tremont St. to Gaston Ave

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
September 17, 2021
Construction Start
February 14, 2022
Expected Completion
August 31, 2024