๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Huffman ISD New Operation Center

25730 WILLY LANE, Huffman, TX 77336, Huffman, TX, 77336
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022001235
$8.0M
Project Value
35,000
Square Feet
$229/sqft
Cost/SqFt
5y 3mo
Duration
Registered:Sep 18, 2021
Start:Oct 5, 2021
Target:Dec 1, 2026
Remaining:344 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

6 NEW BUILDING AND INFRASTRUCTURE

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
September 18, 2021
Construction Start
October 5, 2021
Expected Completion
December 1, 2026