โœ…Inspection Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

TAKE 5 OIL TEXAS CITY

3542 PALMER HIGHWAY, Texas City, TX 77590, Texas City, TX, 77590
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022004289
$600K
Project Value
1,000
Square Feet
$600/sqft
Cost/SqFt
6 months
Duration
Registered:Nov 1, 2021
Start:Feb 1, 2022
Target:Aug 1, 2022
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

NEW OIL CHANGE FACILITY

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 1, 2021
Construction Start
February 1, 2022
Expected Completion
August 1, 2022