๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Kimbo Rd Reconstruction

Kimbo Rd, McComas & Alta View Street, Fort Worth, TX 76111, Fort Worth, TX, 76111
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022004755
$1.0M
Project Value
100
Square Feet
$10.00K/sqft
Cost/SqFt
1y 9mo
Duration
Registered:Nov 6, 2021
Start:Mar 1, 2020
Target:Nov 30, 2021
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Roadway improvements: Paving, drainage, sewer & pedestrian elements

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 6, 2021
Construction Start
March 1, 2020
Expected Completion
November 30, 2021