๐Project Closed๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
A new Store for Toot' n Totum - Bushland
1500 S FM 2381, Bushland, TX 79124, Bushland, TX, 79124
Completed100%
๐Project Metrics
TDLR #TABS2022007421$4.5M
Project Value
7,893
Square Feet
$570/sqft
Cost/SqFt
9 months
Duration
Registered:Dec 15, 2021
Start:Mar 28, 2022
Target:Dec 31, 2022
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Construction of a 7,893 sf convenience store with an end cap quick serve restaurant and each will have a drive up window. There will be an 8 pump gas canopy and 3 pump diesel canopy.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
December 15, 2021
Construction Start
March 28, 2022
Expected Completion
December 31, 2022