๐Project Closed๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Installation/Improvements of Traffic Signals
Various Locations, Dallas, TX 75150, Dallas, TX, 75150
Completed100%
๐Project Metrics
TDLR #TABS2022008797$420K
Project Value
3,000
Square Feet
$140/sqft
Cost/SqFt
2y 6mo
Duration
Registered:Jan 7, 2022
Start:Oct 1, 2022
Target:Apr 1, 2025
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Upgrade/Install 6 traffic signals with pedestrian accessibility
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
January 7, 2022
Construction Start
October 1, 2022
Expected Completion
April 1, 2025
๐Related Projects
๐คSame Owner
$391.1M totalProperty Owner
๐ค
TxDOT District: Dallas
Contact: Corrine Chandler, P.E.
4 projects ยท $391.1M
4777 E US 80, Mesquite, Texas 75150