๐Project Closed๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Coombs Creek Trail Extension
Near N. Beckley Avenue and Oregon Avenue, Dallas, TX 75208, Dallas, TX, 75208
Completed100%
๐Project Metrics
TDLR #TABS2022009627$975K
Project Value
30,000
Square Feet
$33/sqft
Cost/SqFt
2y 5mo
Duration
Registered:Jan 19, 2022
Start:Sep 1, 2022
Target:Feb 1, 2025
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Construction of concrete trail improvements to provide pedestrian and bicycle connectivity between the Kessler Oaks residential neighborhood and the IH 30 Bridge.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
January 19, 2022
Construction Start
September 1, 2022
Expected Completion
February 1, 2025
๐Related Projects
๐คSame Owner
$8.2M total๐๏ธSame Design Firm
$1.3M totalFrankford Park Playground Equipment Replacement Project
Dallasยท$305K
Bent Tree Meadow Park Playground Equipment Replacement Project
Dallasยท$300K
Meadowstone Park - Texas Parks and Wildlife Department Grant Improvements - Group 1
Dallasยท$310K
Danieldale Park - Texas Parks and Wildlife Department Grant Improvements - Group 1
Dallasยท$380K
Property Owner
๐ค
City of Dallas
Contact: Horacio Pizzarello, P.E .
4 projects ยท $8.2M
320 E. Jefferson Blvd. Room 307, Dallas, Texas 75203
Design Firm
๐๏ธ
Urban Engineers Group, Inc.
4 projects ยท $1.3M
167 Turtle Creek Blvd. Ste. A, Dallas, Texas 75207