๐Project Closed๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
HNTB - 21st Floor Build Out
1301 Fannin St, Houston, TX 77002, Houston, TX, 77002
Completed100%
๐Project Metrics
TDLR #TABS2022013467$1.8M
Project Value
15,739
Square Feet
$113/sqft
Cost/SqFt
3 months
Duration
Registered:Mar 7, 2022
Start:Jun 1, 2022
Target:Sep 2, 2022
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Renovation of a portion of the 21st floor of the above mentioned address. The existing build out with be demolished. The new build out will consist of offices, conference rooms, a break area, and workstation installation.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
March 7, 2022
Construction Start
June 1, 2022
Expected Completion
September 2, 2022
๐Related Projects
๐คSame Owner
$2.1M total๐๏ธSame Design Firm
$33.0M totalProperty Owner
๐ค
Netrality Data Centers
Contact: Tracy Nevill
4 projects ยท $2.1M
1301 Fannin St STE 100, Houston, Texas 77002