โœ…Inspection Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Cumby ISD High School & CTE

303 Sayle Street, Cumby, TX 75433, Cumby, TX, 75433
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022014286
$6.0M
Project Value
36,000
Square Feet
$167/sqft
Cost/SqFt
1y 1mo
Duration
Registered:Mar 16, 2022
Start:Apr 15, 2022
Target:Apr 30, 2023
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

New high school and CTE building.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 16, 2022
Construction Start
April 15, 2022
Expected Completion
April 30, 2023