📝Review Complete🔧 Additions to Existing Building💵 This project involves public funds, public land, or is a Federally funded roadway project.

Las Colinas Blvd/Riverside Drive Levee Redesign

850 E Las Colinas Blvd, Irving, TX 75014, Irving, TX, 75014
Construction50%

📊Project Metrics

TDLR #TABS2022014419
$290K
Project Value
8,028
Square Feet
$36/sqft
Cost/SqFt
5 months
Duration
Registered:Mar 18, 2022
Start:May 1, 2022
Target:Sep 30, 2022
📝

Review Complete

Design review complete, construction may proceed

📋Scope of Work

Modify alignment of existing earthen levee within the Las Colinas Urban Center and modify the parking lots associated with the realignment

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

📅Compliance Timeline

Project Registered
March 18, 2022
Construction Start
May 1, 2022
Expected Completion
September 30, 2022