๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

Kellum Schertz MOB

3795 F.M. 3009, Schertz, TX 78154, Schertz, TX, 78154
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022015035
$2.0M
Project Value
9,010
Square Feet
$222/sqft
Cost/SqFt
6 months
Duration
Registered:Mar 28, 2022
Start:May 30, 2022
Target:Nov 30, 2022
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Building Shell for future office / mercantile use. Site Work is under separate permit.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 28, 2022
Construction Start
May 30, 2022
Expected Completion
November 30, 2022