๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

MidTown Village Apartments Phase II

1501 N. Border Ave., Weslaco, TX 78596, Weslaco, TX, 78596
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022015265
$8.0M
Project Value
143,830
Square Feet
$56/sqft
Cost/SqFt
1 year
Duration
Registered:Mar 29, 2022
Start:Jun 1, 2022
Target:Jun 1, 2023
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

New Construction on Green field of 152 Apartment units

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 29, 2022
Construction Start
June 1, 2022
Expected Completion
June 1, 2023