BISD Skinner Elem. Mini Gyms HVAC & Restrooms

411 W St Charles St, Brownsville, TX 78520, Brownsville, TX, 78520
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022015365
$544K
Project Value
900
Square Feet
$604/sqft
Cost/SqFt
9 months
Duration
Registered:Mar 30, 2022
Start:May 1, 2022
Target:Jan 26, 2023
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

The construction includes improvements to the existing building and of the new building attached to the existing gym which will hold the restrooms and the mechanical room for the HVAC.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 30, 2022
Construction Start
May 1, 2022
Expected Completion
January 26, 2023