๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Bear Creek Interceptor, Phase 1 & WF-G Lone Star Trail
N/a, Grand Prairie, TX 75050, Grand Prairie, TX, 75050
Construction50%
๐Project Metrics
TDLR #TABS2022019472$749K
Project Value
89,000
Square Feet
$8/sqft
Cost/SqFt
2y 3mo
Duration
Registered:May 19, 2022
Start:Sep 1, 2022
Target:Nov 30, 2024
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Removal and replacement (56,000SF) of the existing Lone Star Trail generally from Belt Line Road to a pedestrian bridge at Horseshoe Lake and at access points off of Pollock
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
May 19, 2022
Construction Start
September 1, 2022
Expected Completion
November 30, 2024
๐Related Projects
๐คSame Owner
$199.0M total๐๏ธSame Design Firm
$19.0M totalProperty Owner
๐ค
Trinity River Authority of Texas
Contact: Greg A. Vaughn
3 projects ยท $199.0M
5300 S. Colins, Arlington, Texas 76018
Design Firm
๐๏ธ
Lockwood, Andrews and Newnam, Inc.
4 projects ยท $19.0M
13000 Summitt Ave, Suite 300, Fort Worth, Texas 76102