📝Review Complete🏗️ New Construction💵 This project involves public funds, public land, or is a Federally funded roadway project.

Slaughter Lane Corridor Segment C2

3400-5100 Slaughter Lane, Austin, TX 78748, Austin, TX, 78748
Construction50%

📊Project Metrics

TDLR #TABS2022020802
$12.0M
Project Value
1,118,621
Square Feet
$11/sqft
Cost/SqFt
4y 7mo
Duration
Registered:Jun 6, 2022
Start:Dec 2, 2022
Target:Jun 6, 2027
Remaining:531 days
📝

Review Complete

Design review complete, construction may proceed

📋Scope of Work

Bike/ped imp.- addition and/or realignment of 7’ wide sidewalks along roadway; 6.5'+ protected bike lanes with new bike median curb. Ped ramps & driveways reconstructed to comply with ADA. Median realignment work is proposed widening roadway.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

📅Compliance Timeline

Project Registered
June 6, 2022
Construction Start
December 2, 2022
Expected Completion
June 6, 2027