๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

2018 Bond Cameron at Ferguson Intersection Safety Improvements

Cameron Ln and Ferguson Ln, Austin, TX 78746, Austin, TX, 78746
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022022790
$112K
Project Value
1
Square Feet
$111.89K/sqft
Cost/SqFt
4 months
Duration
Registered:Jun 30, 2022
Start:Mar 30, 2022
Target:Jul 18, 2022
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Remove and replace ADA curb ramps, sidewalk, and curb/gutter to improve pedestrian safety.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
June 30, 2022
Construction Start
March 30, 2022
Expected Completion
July 18, 2022