๐Project Closed๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
Jersey Mike's Subs
409 S Central Expressway #105, Anna, TX 75409, Anna, TX, 75409
Completed100%
๐Project Metrics
TDLR #TABS2022022955$175K
Project Value
1,320
Square Feet
$133/sqft
Cost/SqFt
5 months
Duration
Registered:Jul 5, 2022
Start:Sep 1, 2022
Target:Jan 20, 2023
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Tenant finish out of a new retail shell strip center space into a new Jersey Mikes Subs
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
July 5, 2022
Construction Start
September 1, 2022
Expected Completion
January 20, 2023