โœ…Inspection Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

SW Legacy Portables

4495 Verano Pkwy, San Antonio, TX 78073, San Antonio, TX, 78073
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022024049
$70K
Project Value
6,223
Square Feet
$11/sqft
Cost/SqFt
2 months
Duration
Registered:Jul 19, 2022
Start:Aug 1, 2022
Target:Sep 30, 2022
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

relocate four (4) existing portable classroom buildings currently located at another SWISD campus.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 19, 2022
Construction Start
August 1, 2022
Expected Completion
September 30, 2022