๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Huntsville City Hall
1212 Avenue M, Huntsville, TX 75211, Huntsville, TX, 75211
Construction50%
๐Project Metrics
TDLR #TABS2022024518$20.0M
Project Value
39,800
Square Feet
$503/sqft
Cost/SqFt
3y 3mo
Duration
Registered:Jul 25, 2022
Start:Dec 8, 2022
Target:Feb 15, 2026
Remaining:55 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
39,800 GSF new construction for Council Chambers and City Hall Departments. Includes 2 Story Council Chambers, Atrium/Lobby, Customer Service/Utility Billing, Development Services, Engineering,
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
July 25, 2022
Construction Start
December 8, 2022
Expected Completion
February 15, 2026
๐Related Projects
๐คSame Owner
$28.3M total๐๏ธSame Design Firm
$40.2M totalProperty Owner
๐ค
City of Huntsville
Contact: Dr. Kathlie Jeng-Bulloch
4 projects ยท $28.3M
1212 Avenue M, Huntsville, Texas 77340
Design Firm
๐๏ธ
Randall Scott Architects, Inc.
4 projects ยท $40.2M
2140 Lake Park Blvd. Suite 300, Richardson, Texas 75080