๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
City of Venus City Hall Paving
700 US-67, Venus, TX 76084, Venus, TX, 76084
Construction50%
๐Project Metrics
TDLR #TABS2022026479$257K
Project Value
36,810
Square Feet
$7/sqft
Cost/SqFt
5 months
Duration
Registered:Aug 18, 2022
Start:Jan 1, 2023
Target:Jun 1, 2023
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Phase One consists of installing up to approx 15,570SF of asphalt pavement, 2 ADA compliant parking spaces, striping, curb & gutter, etc. Phase Two consists of installing up to approx 21,240SF of asphalt pavement, striping, curb & gutter, etc.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
August 18, 2022
Construction Start
January 1, 2023
Expected Completion
June 1, 2023