๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
TECH-OPS FINISH-OUT, TERMINAL C HIGH C GATES
2330 NORTH INTL PKWY, BLDG I.D. #165, Dfw Airport, TX 75264, Dfw Airport, TX, 75264
Construction50%
๐Project Metrics
TDLR #TABS2023003099$750K
Project Value
5,000
Square Feet
$150/sqft
Cost/SqFt
5 months
Duration
Registered:Oct 13, 2022
Start:Dec 1, 2022
Target:Apr 30, 2023
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Interior finish-out of ramp level interior office/ operations/ break room and storage areas.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
October 13, 2022
Construction Start
December 1, 2022
Expected Completion
April 30, 2023
๐Related Projects
Property Owner
Design Firm
Tenant
๐ข
JOHN HAYWOOD