๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

Allsup's Gas Station #102432 Ennis

US 287 & SH 34, Ennis, TX 75119, Ennis, TX, 75119
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2023003490
$600K
Project Value
5,630
Square Feet
$107/sqft
Cost/SqFt
5 months
Duration
Registered:Oct 19, 2022
Start:Nov 21, 2022
Target:Apr 6, 2023
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

All Architectural, Structural and MEP work of new construction.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
October 19, 2022
Construction Start
November 21, 2022
Expected Completion
April 6, 2023

๐Ÿ“Location & Views

Open in MapsGet Directions|32.32902, -96.62458