๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Malakoff ISD High School

14701 FM 3062, Malakoff, TX 75148, Malakoff, TX, 75148
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2023003827
$71.0M
Project Value
187,000
Square Feet
$380/sqft
Cost/SqFt
1y 10mo
Duration
Registered:Oct 24, 2022
Start:Nov 1, 2022
Target:Aug 31, 2024
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

New high school.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
October 24, 2022
Construction Start
November 1, 2022
Expected Completion
August 31, 2024