๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

Alphabroder / Primeline Dallas DFW Facility

1040 Trade Ave., Dfw Airport, TX 75261, Dfw Airport, TX, 75261
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2023004097
$3.8M
Project Value
167,034
Square Feet
$22/sqft
Cost/SqFt
4 months
Duration
Registered:Oct 27, 2022
Start:Jan 1, 2023
Target:May 1, 2023
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

167034 sq ft

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
October 27, 2022
Construction Start
January 1, 2023
Expected Completion
May 1, 2023