๐Project Closed๐ง Additions to Existing Building๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Tulia ISD Elevator Add
800 NW 9th St., Tulia, TX 79088, Tulia, TX, 79088
Completed100%
๐Project Metrics
TDLR #TABS2023005907$190K
Project Value
250
Square Feet
$760/sqft
Cost/SqFt
1y 8mo
Duration
Registered:Nov 21, 2022
Start:Jan 6, 2023
Target:Aug 30, 2024
๐
Project Closed
Project has been completed and closed
๐Scope of Work
General construction work including, mechanical, plumbing, and electrical for elevator addition.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
November 21, 2022
Construction Start
January 6, 2023
Expected Completion
August 30, 2024