🏁Project Closed🔧 Renovation/Alteration💵 This project is privately funded, on private land for private use.
Apex Clearing
350 N St. Paul Street, Dallas, TX 75201, Dallas, TX, 75201
Completed100%
📊Project Metrics
TDLR #TABS2023006223$1.0M
Project Value
7,100
Square Feet
$141/sqft
Cost/SqFt
5 months
Duration
Registered:Nov 28, 2022
Start:Oct 24, 2022
Target:Mar 24, 2023
🏁
Project Closed
Project has been completed and closed
📋Scope of Work
Refresh space and add 2 restrooms
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
November 28, 2022
Construction Start
October 24, 2022
Expected Completion
March 24, 2023