๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Judson ISD- Middle School # 6
5710 Carriage Cape, San Antonio, TX 78261, San Antonio, TX, 78261
Construction50%
๐Project Metrics
TDLR #TABS2023006861$79.5M
Project Value
189,833
Square Feet
$419/sqft
Cost/SqFt
3 years
Duration
Registered:Dec 6, 2022
Start:Feb 1, 2023
Target:Jan 30, 2026
Remaining:42 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
New Middle School and Site Improvements
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
December 6, 2022
Construction Start
February 1, 2023
Expected Completion
January 30, 2026
๐Related Projects
๐คSame Owner
$923K totalProperty Owner
๐ค
Judson Independent School District
Contact: Helen Keaton
4 projects ยท $923K
7980 Pat Booker Road, Live Oak, Texas 78233
Design Firm
๐๏ธ
Pfluger Architects
4 projects ยท $15.3M
200 E. Grayson Street, San Antonio, Texas 78215