Trane Technologies 9.1 Chemical Building
6200 Troup Hwy, Tyler, TX 75707, Tyler, TX, 75707
Construction50%
๐Project Metrics
TDLR #TABS2023008678$1.5M
Project Value
10,806
Square Feet
$139/sqft
Cost/SqFt
2 months
Duration
Registered:Jan 4, 2023
Start:Jan 15, 2023
Target:Mar 15, 2023
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
New construction of Chemical Storage Building Addition.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
January 4, 2023
Construction Start
January 15, 2023
Expected Completion
March 15, 2023
๐Related Projects
๐คSame Owner
$24.6M totalProperty Owner
๐ค
Trane Technologies
Contact: Roger Bohot
3 projects ยท $24.6M
6200 Troup Hwy, Tyler, Texas 75707
Design Firm
๐๏ธ
Thompson Architectural Group, Inc.
4 projects ยท $13.4M