Construction50%
๐Project Metrics
TDLR #TABS2023009361$98.3M
Project Value
1,077
Square Feet
$91.26K/sqft
Cost/SqFt
2y 6mo
Duration
Registered:Jan 13, 2023
Start:Jun 1, 2023
Target:Dec 1, 2025
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Reconstruct and widen 4 mainlanes to 6, reconstruct and widen 4 lane frontage roads to 4/6 lanes, construct new and reconstruct existing interchanges, ramp modifications and pedestrian improvements.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
January 13, 2023
Construction Start
June 1, 2023
Expected Completion
December 1, 2025