KIEWIT WESTLAKE OFFICE TI - PHASE II

2050 ROANOKE, Westlake, TX 76262, Westlake, TX, 76262
Pre-Construction15%

๐Ÿ“ŠProject Metrics

TDLR #TABS2023009989
$3.2M
Project Value
40,080
Square Feet
$80/sqft
Cost/SqFt
5 months
Duration
Registered:Jan 23, 2023
Start:Jan 30, 2023
Target:Jul 3, 2023
๐Ÿ“‹

Project Registered

Project has been registered with TDLR and is in pre-construction phase

๐Ÿ“‹Scope of Work

Build out existing space in an existing building.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
January 23, 2023
Construction Start
January 30, 2023
Expected Completion
July 3, 2023