๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Los Fresnos North HS Park Connection

FM 1847 Los Fresnos, Los Fresnos, TX 78566, Los Fresnos, TX, 78566
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2023015766
$376K
Project Value
20,394
Square Feet
$18/sqft
Cost/SqFt
4 months
Duration
Registered:Apr 4, 2023
Start:Aug 1, 2023
Target:Dec 1, 2023
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Construction of curb ramps, sidewalks, traffic poles, striping along FM 1847

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
April 4, 2023
Construction Start
August 1, 2023
Expected Completion
December 1, 2023