๐Ÿ“‹Project Registered๐Ÿ”ง Additions to Existing Building๐Ÿ’ต This project is privately funded, on private land for private use.

CyrusOne - SATV - 1.5MW Load Adder

Zeta Drive, San Antonio, TX 78245, San Antonio, TX, 78245
Pre-Construction15%

๐Ÿ“ŠProject Metrics

TDLR #TABS2023017499
$4.5M
Project Value
1,078
Square Feet
$4.14K/sqft
Cost/SqFt
3 months
Duration
Registered:Apr 25, 2023
Start:May 22, 2023
Target:Aug 31, 2023
๐Ÿ“‹

Project Registered

Project has been registered with TDLR and is in pre-construction phase

๐Ÿ“‹Scope of Work

This project proposes to construct two equipment lineups in the equipment yard on the existing 2-Story Data Center. Two chillers will be installed on the roof to support the new equipment lineups.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
April 25, 2023
Construction Start
May 22, 2023
Expected Completion
August 31, 2023