36-INCH WATER LINE ALONG MEDICAL CENTER BLVD, CHANNEL A111-00-00 AND BAY AREA BLVD
522 BLOSSOM ST, WEBSTER, TX, 77598, Webster, TX 77598, Webster, TX, 77598
Construction50%
๐Project Metrics
TDLR #TABS2023020781$150K
Project Value
12,059
Square Feet
$12/sqft
Cost/SqFt
1y 9mo
Duration
Registered:Jun 6, 2023
Start:Oct 30, 2024
Target:Jul 7, 2026
Remaining:197 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
REMOVAL AND REPLACEMENT OF APPROX. 12059 SF OF EXISTING SIDEWALK ALONG PROJECT LIMITS FOR PROPOSED 36-INCH WATERLINE. PROJECT LIMITS BEGIN AT INTERSECTION OF BEAMER RD @ BAY AREA BLVD AND END AT INTERSECTION OF ORCHARD ST @ GALVESTON BLVD.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
June 6, 2023
Construction Start
October 30, 2024
Expected Completion
July 7, 2026
๐Related Projects
Property Owner
๐ค
CITY OF HOUSTON PUBLIC WORKS
Contact: ANH BOYD
3 projects ยท $15.6M