📝Review Complete🔧 Renovation/Alteration💵 This project is privately funded, on private land for private use.
Restroom Addition
516 E. Beech St., Mcallen, TX 78501, Mcallen, TX, 78501
Construction50%
📊Project Metrics
TDLR #TABS2023022003$160K
Project Value
748
Square Feet
$214/sqft
Cost/SqFt
8 months
Duration
Registered:Jun 22, 2023
Start:Jun 20, 2023
Target:Feb 1, 2024
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
Addition of new restrooms.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
June 22, 2023
Construction Start
June 20, 2023
Expected Completion
February 1, 2024