๐Project Closed๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
TAMU Dunn Hall SM 2024 Finishes Renovation, Ph 2
636 Lubbock Street, College Station, TX 77843, College Station, TX, 77843
Completed100%
๐Project Metrics
TDLR #TABS2023022553$5.2M
Project Value
53,200
Square Feet
$97/sqft
Cost/SqFt
4 months
Duration
Registered:Jun 29, 2023
Start:May 1, 2024
Target:Aug 30, 2024
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Renovation of an existing dorm building with new finishes
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
June 29, 2023
Construction Start
May 1, 2024
Expected Completion
August 30, 2024
๐Related Projects
๐คSame Owner
$1.4M totalProperty Owner
๐ค
TAMU SSC Service Solutions
Contact: Michael Garon
4 projects ยท $1.4M
600 Agronomy Road TAMU MS 1371, College Station, Texas 77843
Design Firm
๐๏ธ
Patterson Architects
4 projects ยท $4.1M
701 South Texas Avenue., Bryan, Texas 77803