โœ…Inspection Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

Suite 130

10810 West Little York, Suite 130, Houston, TX 77041, Houston, TX, 77041
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2023025045
$150K
Project Value
63,000
Square Feet
$2/sqft
Cost/SqFt
3 months
Duration
Registered:Aug 3, 2023
Start:Oct 4, 2023
Target:Dec 18, 2023
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Existing warehouse building interior renovation

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
August 3, 2023
Construction Start
October 4, 2023
Expected Completion
December 18, 2023