๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Five Mile Infrastructure Improvements- Project 2 Pavement and Drainage Improvements Tracy Road
N/A, Dallas, TX 75241, Dallas, TX, 75241
Construction50%
๐Project Metrics
TDLR #TABS2023025318$6.3M
Project Value
14,000
Square Feet
$450/sqft
Cost/SqFt
3y 11mo
Duration
Registered:Aug 7, 2023
Start:Dec 1, 2023
Target:Oct 1, 2027
Remaining:651 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Pavement and Drainage Improvements
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
August 7, 2023
Construction Start
December 1, 2023
Expected Completion
October 1, 2027
๐Related Projects
๐คSame Owner
$8.2M totalProperty Owner
๐ค
City of Dallas
Contact: Samrawit Haile
4 projects ยท $8.2M