🏁Project Closed🏗️ New Construction💵 This project is privately funded, on private land for private use.
Dominique C. Hunt
11220 Panther Creek Parkway, Suite 100, Frisco, TX 75035, Frisco, TX, 75035
Completed100%
📊Project Metrics
TDLR #TABS2023026771$320K
Project Value
2,046
Square Feet
$156/sqft
Cost/SqFt
4 months
Duration
Registered:Aug 25, 2023
Start:Sep 29, 2023
Target:Jan 31, 2024
🏁
Project Closed
Project has been completed and closed
📋Scope of Work
Interior Finish out Dental Office
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
August 25, 2023
Construction Start
September 29, 2023
Expected Completion
January 31, 2024