๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
John Lewis Social Justice Academy at OW Holmes - Org #051
2001 E Kiest Blvd, Dallas, TX 75216, Dallas, TX, 75216
Construction50%
๐Project Metrics
TDLR #TABS2024000226$59.6M
Project Value
160,779
Square Feet
$371/sqft
Cost/SqFt
1y 4mo
Duration
Registered:Sep 6, 2023
Start:Mar 25, 2024
Target:Jul 28, 2025
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Demolition of Existing Middle School. New Construction for Replacement Middle School
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
September 6, 2023
Construction Start
March 25, 2024
Expected Completion
July 28, 2025
๐Related Projects
๐คSame Owner
$70.8M totalProperty Owner
๐ค
Dallas ISD
Contact: Kathleen Lenihan
4 projects ยท $70.8M
9400 North Central Expressway, Suite 800, Dallas, Texas 75231
Design Firm
๐๏ธ
VLK Architects Inc
4 projects ยท $39.8M
5801 Tennyson Pkwy #100, Plano, Texas 75024