๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

Bolton Road Industrial Park Buildings 3&4 Phase 1

799 Bolton Road, Cibolo, TX 78106, Cibolo, TX, 78106
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024002335
$21.0M
Project Value
349,947
Square Feet
$60/sqft
Cost/SqFt
1 year
Duration
Registered:Oct 4, 2023
Start:Nov 1, 2023
Target:Nov 1, 2024
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Spec Warehouse & Office Shell buildings = Building 3 = 152,266sf & Building 4 = 197,681sf

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
October 4, 2023
Construction Start
November 1, 2023
Expected Completion
November 1, 2024

๐Ÿ”—Related Projects

๐Ÿ›๏ธSame Design Firm

$22.3M total