Inspection Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Aubrey ISD | New Middle School No. 2
FM 2931, Aubrey, TX 76227, Aubrey, TX, 76227
Final Inspection85%
๐Project Metrics
TDLR #TABS2024004588$6.7M
Project Value
144,408
Square Feet
$46/sqft
Cost/SqFt
1y 8mo
Duration
Registered:Nov 2, 2023
Start:Nov 21, 2023
Target:Jul 7, 2025
โ
Inspection Complete
Final inspection completed, awaiting project closure
๐Scope of Work
New Middle School No. 2.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
November 2, 2023
Construction Start
November 21, 2023
Expected Completion
July 7, 2025
๐Related Projects
๐คSame Owner
$108.3M total๐๏ธSame Design Firm
$18.7M totalProperty Owner
๐ค
Aubrey ISD
Contact: Dr. David Belding
4 projects ยท $108.3M
415 Tisdell Lane, Aubrey, Texas 76227
Design Firm
๐๏ธ
Huckabee
4 projects ยท $18.7M
801 Cherry Street Ste. 500, Fort Worth, Texas 76102