๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Northpointe East Tract Public Infrastructure
Northpointe East Tract, Pflugerville, TX 78660, Pflugerville, TX, 78660
Construction50%
๐Project Metrics
TDLR #TABS2024005440$3.6M
Project Value
181,210
Square Feet
$20/sqft
Cost/SqFt
3y 2mo
Duration
Registered:Nov 15, 2023
Start:Dec 1, 2023
Target:Dec 31, 2026
Remaining:374 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Construction of public roads, sidewalk, and detention pond, along with necessary storm pipes, wastewater mains and water pipes/fire hydrants
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
November 15, 2023
Construction Start
December 1, 2023
Expected Completion
December 31, 2026
๐Related Projects
Property Owner
๐ค
Verdot at Pflugerville East LLC & Kedma Ventures
Contact: Yariv Bensira
477 Madison Ave, 6th Floor, New York, New York 10022
Design Firm
๐๏ธ
Pape-Dawson Engineers
4 projects ยท $18.4M
10801 N Mopac Expy, Bldg 3, Ste 200, Austin, Texas 78759