๐Review Complete๐ง Additions to Existing Building๐ต This project is privately funded, on private land for private use.
Good Shepherd Episcopal School - Gymnasium
11110 Midway Road, Dallas, TX 75229, Dallas, TX, 75229
Construction50%
๐Project Metrics
TDLR #TABS2024006927$6.8M
Project Value
16,655
Square Feet
$408/sqft
Cost/SqFt
1y 2mo
Duration
Registered:Dec 7, 2023
Start:Jun 3, 2024
Target:Aug 4, 2025
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
New Gymnasium Building that includes a classroom, office, locker room, toilet facilities and storage. Gym to serve as a tornado shelter. Existing lockers rooms in adjacent building to be renovated into classroom.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
December 7, 2023
Construction Start
June 3, 2024
Expected Completion
August 4, 2025
๐Related Projects
๐คSame Owner
$7.4M totalProperty Owner
๐ค
Good Shepherd Episcopal School
Contact: Amanda Medina
3 projects ยท $7.4M
11110 Midway Road, Dallas, Texas 75229
Design Firm
๐๏ธ
Kirksey Architecture
4 projects ยท $24.9M
143 Manufacturing Street, Dallas, Texas 75207