SL 288 ( CSJ: 2250-02-013, etc )

Fr.: IH 35W S of Denton To: IH 35 at LP 288, Denton, TX 76201, Denton, TX, 76201
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024009446
$214.2M
Project Value
83,945
Square Feet
$2.55K/sqft
Cost/SqFt
1y 1mo
Duration
Registered:Jan 17, 2024
Start:Oct 1, 2034
Target:Oct 30, 2035
Remaining:3602 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Construction of interchange and frontage roads.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
January 17, 2024
Construction Start
October 1, 2034
Expected Completion
October 30, 2035