๐Review Complete๐ง Additions to Existing Building๐ต This project involves public funds, public land, or is a Federally funded roadway project.
City of Irving Fleet Maintenance Facility Phase 2
108 N. Briery Rd., Irving, TX 75061, Irving, TX, 75061
Construction50%
๐Project Metrics
TDLR #TABS2024011134$3.4M
Project Value
11,107
Square Feet
$306/sqft
Cost/SqFt
10 months
Duration
Registered:Feb 8, 2024
Start:May 1, 2025
Target:Mar 1, 2026
Remaining:69 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
11,107sf expansion to the existing fleet maintenance facility for the addition of 8 heavy duty vehicle maintenance bays.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
February 8, 2024
Construction Start
May 1, 2025
Expected Completion
March 1, 2026
๐Related Projects
๐คSame Owner
$87.7M totalProperty Owner
๐ค
City of Irving
Contact: Brad Hughes
4 projects ยท $87.7M
825 West Irving Boulevard, Irving, Texas 75060
Design Firm
๐๏ธ
Elements of Architecture
4 projects ยท $21.8M
1201 6th Avenue, Fort Worth, Texas 76104